In the Netherlands a 485 km (300 mi.), 48 inch diameter, high pressure (8 Mpa, 1200 PSI), natural gas pipeline is being constructed. A large part (> 15%) of the pipeline is constructed trenchless in which horizontal directional drillings (HDD) up till 1400 m (4600 feet) length are used. This way of constructing is not only demanding from a construction point of view but also set high demands on the quality and strength of the coating of the steel pipes that is used. For this task, dedicated mill and field joint coating systems were selected. Partly the selected coating systems are new in the industry.

In the paper an overview is given of:

  • the different constructions used and the demands they deliver for the coating

  • the coating systems chosen, both mill and field coating

  • the quality checks involved

  • tests and results

  • experiences, conclusions and outlook for the future.

You do not currently have access to this content.